Protect the Collective - Marrietta
HAPPENING NOW
π’ DATA CENTER β POWERS FERRY PLACE
STATUS: π΄ APPROVED β CONTINUED PUBLIC OVERSIGHT
Case: Z2026-12
Location: Prime Storage, 1155 Powers Ferry Place, Marietta, GA 30067. The application concerns converting part of the existing storage property into a data-infrastructure facility.
WHAT HAPPENED?
July 1 β Planning Commission
The Planning Commission recommended approval 4β3.
July 8 β City Council
A large opposition turnout occurred at Marietta City Hall, including protesters outside and a standing-room-only crowd inside. Council voted 7β0 to table the application, delaying the final decision until August.
August 12 β City Council
Council ultimately approved Z2026-12 5β2, with numerous conditions attached to the project. These included restrictions concerning municipal water for cooling, sound monitoring, an independent acoustic study, generator/emissions requirements and a heat-island study.
COUNSEL MEMBERS VOTING YES
Jason Waters β Ward 2:
Byron βTeeβ Anderson β Ward 4: tanderson@mariettaga.gov
M. Carlyle Kent β Ward 5: mckent@mariettaga.gov
Andre L. Sims β Ward 6:
Joseph R. Goldstein β Ward 7: jgoldstein@mariettaga.gov
*COPY/PASTE EMAIL FOR COUNSEL MEMBERS*
Dear Council Member,
I am writing to ask you to take every lawful action available to prevent the proposed data center at 1155 Powers Ferry Place (Z2026-12) from moving forward.
I understand that City Council approved the rezoning on August 12 by a 5β2 vote. That vote does not erase the significant public opposition or the concerns residents have raised regarding energy demand, noise, generator emissions, heat, infrastructure, environmental impacts, and long-term effects on surrounding communities.
Marietta has already recognized the need for greater scrutiny of data-center development by adopting a moratorium on new applications through the end of 2026.
I am asking you to publicly identify and pursue any lawful remaining avenues available to stop this project from reaching construction or operation, including reconsideration where legally available and appropriate, rigorous review of subsequent permits, utility agreements, infrastructure approvals, environmental requirements, and compliance with every condition attached to Z2026-12.
I also ask the City to make all subsequent contracts, studies, permits, utility commitments, compliance documents, and major decisions concerning this facility readily accessible to the public.
Please provide residents with a clear answer:
What lawful options remain for the City to prevent the 1155 Powers Ferry Place data center from proceeding, and which of those actions are you personally willing to support?
I am asking you to reconsider your support for this project and stand with residents calling for it to be stopped.
Thank you for your time and public service.
Sincerely,
[NAME]
[WARD / NEIGHBORHOOD]
[EMAIL β OPTIONAL]
β‘ WHAT'S HAPPENING NOW?
The issue has moved beyond the original zoning decision into implementation and oversight.
On September 3, the Marietta Board of Lights and Water agenda included consideration of a large-load electric-service contract for 1155 Powers Ferry Place. The agenda also included a data-center moratorium item.
CURRENT WATCH ITEMS
β‘ Electricity / large-load agreements
π Independent acoustic study
π‘οΈ Heat-island study
π¨ Generator/emissions requirements
π§ Cooling/water compliance
π Compliance with City stipulations
ποΈ Permits/construction milestones
ποΈ Data-center moratorium & future applications
TAKE ACTION
π NORTH AVENUE / LEWIS PARK REZONING
CASE: Z2026-22
LOCATION: 673 North Avenue, Marietta, GA
STATUS: PENDING β PUBLIC ACTION CAN STILL INFLUENCE THE DECISION
WHAT'S HAPPENING?
A rezoning request involving 16 parcels near Lewis Park seeks to change the properties from R-2 residential zoning to CRC (Community Retail Commercial).
Some neighborhood residents are organizing against the rezoning and are asking Marietta officials to maintain the existing residential zoning. Residents have raised concerns about increased development intensity, traffic, pedestrian safety, and impacts on the surrounding neighborhood.
This proposal has not received final approval.
π UPCOMING PUBLIC HEARINGS
PLANNING COMMISSION
October 6, 2026 Β· 6:00 PM
π Marietta City Hall
205 Lawrence Street
Marietta, GA 30060
CITY COUNCIL
October 14, 2026 Β· 7:00 PM
π Marietta City Hall
205 Lawrence Street
Marietta, GA 30060
Public participation before these decisions can matter.
π£οΈ COMMUNITY RESPONSE
Neighborhood residents have already organized a petition asking the Planning Commission and City Council to deny Z2026-22 and retain the existing residential zoning.
The petition has been acknowledged by Marietta Planning & Zoning, and residents were informed that the signed petition would be included in the zoning case file.
β HOW YOU CAN PARTICIPATE
1. LEARN
Review the zoning proposal and understand what changing the property from residential to commercial zoning would allow.
2. ATTEND
Attend the October 6 Planning Commission hearing and October 14 City Council hearing.
3. SPEAK
Residents can participate in the public process and communicate their position to local decision-makers.
4. CONTACT
Contact Marietta officials before the hearings and respectfully explain whether you support or oppose Z2026-22 and why.
5. FOLLOW THE CASE
Watch for staff recommendations, changes to the application, meeting agendas, postponements, and the eventual vote.
π VERIFY & LEARN MORE
Marietta Upcoming Zoning Hearings:
https://www.mariettaga.gov/1439/Upcoming-Hearings
Community Petition β Protect Our Historic Marietta Neighborhood From Rezoning:
https://www.change.org/p/protect-our-historic-marietta-neighborhood-from-rezoning
PROTECT THE COLLECTIVE PRINCIPLE
Know what's happening. Read the evidence. Hear your neighbors. Contact decision-makers. Show up before the decision is made.
π WEST OAK DRIVE REZONING
CASE: Z2026-21
LOCATION: 1516 West Oak Drive, Marietta, GA 30062
STATUS: PENDING β CITY COUNCIL VOTE SEPTEMBER 9
WHAT'S HAPPENING?
A property at 1516 West Oak Drive is requesting rezoning from R-2 residential to CRC (Community Retail Commercial).
The Marietta Planning Commission did not recommend the requested CRC commercial zoning as submitted. Instead, it recommended amended approval under OI (Office Institutional) zoning.
That distinction matters because the zoning classification determines what kinds and intensity of future uses can occur on the property.
The final decision has not been made.
β οΈ WHY THIS DESERVES PUBLIC ATTENTION
Rezoning can permanently change what a property may be used for long after the current owner or business leaves.
Before approving a broader commercial designation, residents should be able to understand:
β’ What development or business use is actually being proposed
β’ Why CRC commercial zoning was requested
β’ Why the Planning Commission recommended OI instead
β’ What additional uses CRC would permit in the future
β’ How surrounding residential properties could be affected
β’ Whether a more limited zoning classification can accomplish the applicant's legitimate needs
This is an opportunity for residents to participate before the final decision is made.
π FINAL CITY COUNCIL HEARING
SEPTEMBER 9, 2026 Β· 7:00 PM
π Marietta City Hall
205 Lawrence Street
Marietta, GA 30060
CITY COUNCIL IS EXPECTED TO CONSIDER Z2026-21 AT THIS MEETING.
β HOW YOU CAN PARTICIPATE
1. READ THE APPLICATION
Understand exactly what the applicant is requesting and what uses the requested zoning could permit.
2. REVIEW THE PLANNING COMMISSION RECOMMENDATION
The Planning Commission recommended OI rather than the requested CRC designation. Residents should understand why before the City Council makes its decision.
3. CONTACT CITY COUNCIL
Ask council members to explain whether they support CRC, OI, denial, or another alternativeβand why.
4. ATTEND THE SEPTEMBER 9 HEARING
Residents can attend the City Council meeting and participate in the public process before the final decision.
5. WATCH THE VOTE
Protect the Collective will track the final decision and how elected officials vote.
π VERIFY THE INFORMATION
The City of Marietta lists Z2026-21 as a pending rezoning scheduled for the September 9, 2026 City Council meeting.
VIEW OFFICIAL CITY RECORDS:
Marietta Planning & Zoning β Upcoming Hearings
PROTECT THE COLLECTIVE PRINCIPLE
Public participation should happen before decisions become permanent.
Learn what is being proposed.
Read the record.
Ask questions.
Hear your neighbors.
Show up.
Then decide where you stand.